Battery Playscape
A 1.5-acre flood-resilient playground replacing the one wrecked by Hurricane Sandy's floodwaters, at triple the size, with five ecological zones designed to absorb and withstand flooding. Included here as the tracked project that landed on the budget set at its groundbreaking, though it opened about nine months after the March 2021 completion NYC Parks projected.
$18M
first public estimate, Mar 2020
$18M
reported cost, Dec 2021
Mar 2021
completion promised at announcement
Dec 16, 2021
actual completion, 1 year late
Before the Playscape
The old playground in July 2019, and its site fenced for construction that August.


The schedule
The construction window announced when the project was unveiled, against what actually happened.
Promised versus delivered
What was promised
- A flood-resilient replacement for the Sandy-damaged playground
- Triple the size of the playground it replaced
- Five ecological play zones, from granite slides on the Bluff to salt-tolerant gardens in the Marsh
What happened
- keptOpened December 16, 2021, at the promised $18.3M
- keptDelivered at triple the previous playground's size, with all five ecological zones built
- changedOpened about nine months after the March 2021 completion NYC Parks projected when construction began in December 2019; the agency's capital tracker notes that the completion date changed
Sources
- Official project page
- NYC Parks and The Battery Conservancy open the Battery Playscape
- New $18.3M sustainable playground opens at the Battery, 6sqft
- The Battery Playscape opens, born of the floodwaters of Hurricane Sandy, Tribeca Trib
- Battery Park Playground Reconstruction, NYC Parks capital project tracker: construction from December 2019, projected completion March 2021
- NYC Parks and The Battery Conservancy break ground on the Battery Playscape, March 12, 2020